How Long Does a Kitchen Remodel Take? A Week by Week Timeline

A kitchen remodel takes 8 to 14 weeks of construction plus 6 to 12 weeks of design and lead time before demolition. Here is the week by week sequence and where it actually slips.

HK H&C Kitchen & Bath Design Team · Showroom Design Center
Published Aug 25, 2026 · 5 min read

A kitchen remodel takes 8 to 14 weeks of active construction, plus 6 to 12 weeks before demolition for design, selections, permits, and cabinet lead time. Total elapsed time is typically 4 to 6 months. The two phases that slip most often are cabinet lead time and countertop templating, and both are predictable enough to plan around.

A timeline is only useful when it is built against your house. Permit scope, existing conditions, and lead times all shift the dates. Ask H&C Construction for a schedule built on your actual project.

Almost every timeline that goes badly went badly before demolition. Homeowners measure the project from the day the crew arrives. The schedule is actually set weeks earlier, when selections were or were not finalized.

The full timeline

Phase Duration What happens
Design and layout 2 to 4 weeks Measure, draft, revise, approve
Selections 2 to 3 weeks Cabinets, counters, tile, flooring, fixtures, appliances
Cabinet order and lead time 4 to 10 weeks Runs in parallel with permits
Permit review 2 to 6 weeks Montgomery County, varies by scope
Demolition 2 to 4 days Plus disposal
Rough-in: plumbing, electrical, HVAC 1 to 2 weeks Inspection follows
Drywall and prep 1 week Patch, float, prime
Flooring 3 to 5 days Often before cabinets
Cabinet installation 3 to 7 days Depends on run length and complexity
Countertop template 1 day Cannot happen before cabinets are set
Countertop fabrication 1 to 2 weeks Off-site
Countertop installation 1 day
Backsplash tile 2 to 4 days After counters
Plumbing and electrical trim 2 to 4 days Fixtures, outlets, lighting
Appliance installation 1 to 2 days
Paint, punch list, final inspection 1 week

The two bottlenecks, and how to defuse them

Cabinet lead time

Cabinets are the long pole. Stock and quick-ship lines can arrive in 1 to 3 weeks. Semi-custom typically runs 4 to 8 weeks. Custom runs 8 to 16 weeks or longer.

Defuse it by ordering cabinets before permits are approved, not after. The two processes are independent, and running them in sequence rather than in parallel is the most common self-inflicted delay we see. It routinely costs a month.

This is also the argument for selecting from lines a showroom actually stocks and orders regularly. We know current lead times on Fabuwood, Forevermark, Cubitac, Medallion, and St. Martin because we place orders weekly, not because a catalog says so.

Countertop templating

Countertops cannot be templated until cabinets are installed and level. Template to installation is typically 7 to 14 days. There is no way to compress this, and no honest fabricator will template from drawings for a stone top.

Plan for a functional gap. You will have cabinets and no counters for one to two weeks. A temporary plywood top and a plan for how you will wash dishes makes this survivable.

Where the schedule actually breaks

Selections not finalized before demolition. The single largest cause of delay. Every unmade decision becomes a stop-work moment later.

Change orders mid-project. Moving an outlet after drywall means opening drywall. Changing a cabinet after delivery means a new lead time.

Discovery at demolition. In Montgomery County homes built before 1978, expect at least one of: outdated wiring, galvanized supply lines, subfloor damage, or asbestos-containing floor tile. Asbestos abatement adds days and requires a licensed contractor.

Inspection scheduling. Rough-in inspection has to pass before drywall. Build slack around inspection dates rather than assuming same-week availability.

Appliance availability. Specialty and professional appliances can carry long lead times. Confirm before finalizing the cabinet plan, since appliance dimensions drive cabinet openings.

A realistic pre-construction checklist

Complete all of this before demolition day:

  1. Final measured drawings approved
  2. Cabinet line, door style, finish, and full configuration ordered
  3. Countertop material selected and slab viewed if it is natural stone
  4. Flooring selected and on site or scheduled
  5. Tile and grout color selected
  6. All plumbing fixtures selected, with model numbers, so rough-in dimensions are known
  7. All appliances selected, with spec sheets, so openings and utilities are correct
  8. Lighting plan finalized including switch locations
  9. Permits submitted
  10. A working kitchen plan: where the microwave, fridge, and coffee maker will live for three months

Items 6 and 7 are the ones people skip. Rough-in cannot be done correctly without model numbers, and guessing means opening walls later.

Can it be done faster?

Yes, under specific conditions: a cosmetic refresh with quick-ship cabinets, no plumbing or electrical changes, and no permit requirement can be done in 3 to 5 weeks. That is a genuinely different project from a full renovation.

What does not work is compressing a full renovation by starting before selections are complete. It feels faster for two weeks and then costs a month.

Frequently asked questions

How long does a kitchen remodel take from start to finish?

A full kitchen remodel takes 4 to 6 months of total elapsed time: 6 to 12 weeks for design, selections, permits, and cabinet lead time, then 8 to 14 weeks of construction. A cosmetic refresh with quick-ship cabinets and no permits can be completed in 3 to 5 weeks.

Why does a kitchen remodel take so long?

The two longest phases are cabinet manufacturing lead time, typically 4 to 10 weeks, and countertop fabrication, which requires templating after cabinets are installed and adds 1 to 2 weeks. Permit review and inspection scheduling add further fixed time that cannot be compressed.

How long are you without a kitchen during a remodel?

Plan on 8 to 14 weeks without a functional kitchen, including a 1 to 2 week window with cabinets installed but no countertops while the stone is fabricated. Setting up a temporary kitchen with a microwave, refrigerator, and washing plan is worth doing before demolition.

Should I order cabinets before permits are approved?

Yes. Cabinet lead time and permit review run independently, so ordering cabinets while permits are under review typically saves a month. Sequencing them one after the other is the most common avoidable delay in kitchen remodeling.

Want a schedule built against real lead times? We order from these cabinet lines weekly and know what is actually shipping. Call (301) 939-0009 or book a showroom visit.

HK
Written by

H&C Kitchen & Bath Design Team

The H&C Kitchen & Bath design team helps homeowners and trade pros across the DMV plan kitchens and baths — cabinets, countertops, tile, flooring and more — from our Derwood, MD showroom.